Maersk’s 6 November 2026 North American Market Update reported that AI-related goods accounted for 29.7% of U.S. air import volumes by weight in the second quarter of 2026, up from 27.4% in the first quarter. The company also cited strong growth in global airfreight demand excluding low-value goods, with North American imports rising sharply in July and August. The implication is straightforward: the buildout of AI infrastructure depends on a large physical supply chain, not only software and cloud services.

Semiconductors, servers, networking equipment, power systems and cooling components can be time-sensitive, high-value cargo. They compete for aircraft capacity and careful handling. The effect on any other shipper depends on route, season, product and service choice, but procurement teams should not assume that airfreight capacity is insulated from technology-sector demand.

Map exposure by lane and urgency

Start by listing shipments for which airfreight is essential, shipments that could move by sea or rail, and shipments where only a small quantity needs to arrive quickly. Separate the cost of the item from the cost of delay. For production-critical components, a late delivery can stop an entire line; for other goods, a few days may be manageable if inventory and customer commitments allow it.

Segment demand by origin, destination, required delivery date, dimensional weight, handling needs and security requirements. A general statement that “air capacity is tight” is not enough to change a plan. Ask forwarders which services and departures are affected and whether the constraint is aircraft space, connection availability, ground handling or destination delivery.

Forecast earlier and share a credible demand signal

Providers can plan capacity more effectively when shippers share realistic forecasts and update them when demand changes. Send a rolling view of expected weekly volumes, peak dates and priority shipments. Avoid inflating forecasts to reserve space; that can damage allocation credibility and leave other parts of the plan uncoordinated.

For critical cargo, obtain a booking confirmation and clarify what it guarantees. A quote, a booking request and confirmed uplift are not the same status. Agree when the forwarder must notify you of a roll, a missed connection or a schedule change, and identify the escalation contact before the cargo is tendered.

Use selective mode shifts rather than blanket expediting

When air capacity or pricing becomes uncertain, consider moving predictable, non-urgent volume by ocean or another suitable mode while preserving airfreight for the most time-sensitive units. A split shipment can protect production without paying premium rates on the entire order. The calculation should include inventory carrying cost, packaging, insurance, customs, handling and the risk of separate deliveries.

Mode changes are not interchangeable across all products. Battery restrictions, temperature control, dangerous-goods rules, security requirements and product shelf life can limit the options. Confirm technical and regulatory eligibility before comparing rates. For very high-value goods, include secure handling and insurance terms in the comparison.

Review routing and connection risk

A lower rate may involve a longer connection or fewer recovery options if a flight is missed. Ask providers to compare the full routing, scheduled transit time, connection buffer, cut-off times and recent performance. If a route depends on one hub, identify an alternative that can be activated without restarting the entire shipment process.

For cargo already moving, track milestones and the last confirmed event. If a shipment is delayed, compare the cost of waiting with the cost and feasibility of rerouting. Do not authorize a route change based on a verbal estimate alone; request the new itinerary, revised arrival range and incremental charges in writing.

Protect budgets from emergency-rate creep

Separate planned airfreight from exception shipments in the logistics budget. Track the reason for each expedite, who approved it and what business loss it avoided. This creates evidence for deciding whether a buffer stock, supplier relocation, alternate transport mode or revised production schedule is cheaper than repeated emergency shipments.

Where suppliers control freight, ask for clear service levels and visibility into shipment status. Where the buyer controls freight, ensure purchase orders state the required delivery date, handover point and responsibility for export documents. Unclear ownership can turn a capacity problem into a claims dispute.

Buyer checklist

  • Identify which products genuinely require airfreight and which can move by another mode.
  • Share realistic volume forecasts and confirm uplift, not only a quoted rate.
  • Compare routes by reliability, connections and total landed cost.
  • Keep a pre-approved contingency for critical components.
  • Review expedite spend monthly and remove recurring root causes.

AI-related cargo growth does not mean every airfreight lane will be constrained. It does mean capacity planning should be more specific. Buyers that forecast early, prioritize by consequence and keep alternatives qualified are better positioned when premium capacity becomes competitive.

Sources

Market information only. This article is for general information and is not legal, financial or compliance advice. Verify current data, contractual terms and applicable requirements before acting.